10,192Students, 2025-26
5,531In 10 elementary schools (TK to 6)
1,563In 2 middle schools (7 to 8)
3,084In Milpitas High, Calaveras Hills and Middle College
Enrollment by school
2025-26 census day enrollment.
Source: California Department of Education, DataQuest, 2025-26 enrollment by grade.
Buildings by site
Approximate building square feet for every site, and square feet per student where the site is a single school.
| Site | Type | Building SF | SF per student |
|---|---|---|---|
| William Burnett Elementary | Elementary | 50,990 | 112 |
| Curtner Elementary | Elementary | 48,853 | 74 |
| Marshall Pomeroy Elementary | Elementary | 53,598 | 89 |
| Mabel Mattos Elementary | Elementary | 19,700 | 26 |
| Robert Randall World Languages | Elementary | 39,865 | 132 |
| Alexander Rose Elementary | Elementary | 58,871 | 124 |
| John Sinnott Elementary | Elementary | 56,253 | 80 |
| Anthony Spangler Elementary | Elementary | 59,025 | 101 |
| Joseph Weller Elementary | Elementary | 54,203 | 126 |
| Pearl Zanker Elementary | Elementary | 58,337 | 102 |
| Rancho Milpitas Middle | Middle | 62,777 | 87 |
| Thomas Russell Middle | Middle | 67,637 | 81 |
| Milpitas High | High | 254,383 | 88 |
| Innovation Campus (high school, adult education, district office) | Campus | 119,494 | |
| Corp Yard (maintenance, nutrition, warehouse) | Support | 14,175 | |
| Rose Child Development Center | Child development | 11,980 | |
| Sunnyhills Child Development Center | Child development | 9,100 | |
| Total | 1,039,241 |
Sources: building area, RFQ/P Addendum No. 2 (November 10, 2026); enrollment, CDE DataQuest 2025-26.
Local bonds
| Measure | Election | Amount |
|---|---|---|
| Measure E | June 2012 | $95 million |
| Measure AA | November 2018 | $284 million |
Source: musd.org, Bond and Construction.
State funding
The district received $23,980,633 from Proposition 1A for projects from its 1996 bond, and applied for State School Facility Program funds for the Mabel Mattos Elementary new construction project ($16.8 million application). The district estimates its facility needs at over $760 million.
Source: musd.org, State Matching Funds.